Q: 1
A risk manager is facilitating a risk identification workshop on a new product with technical experts. There is no consensus among the technical experts on most of the identified risks and their characteristics. The risk manager decides to resolve this difference using another technique. Which technique should the risk manager use in this situation?
Options
Q: 2
The project team has correctly identified, assessed, and planned responses for a project's risks. The risk manager is required to prepare a quarterly report on the performance of managing the risks. What are two options the risk manager should consult for the analysis? (Choose two.)
Options
Q: 3
A risk manager for a new product development project has worked diligently with stakeholders and the project team to identify and document risks. These project risks vary widely in probability and impact. Which three actions should the risk manager take to inform the identification of resource requirements for individual risk responses? (Choose 3).
Options
Q: 4
A risk manager administered a pre-workshop risk survey in preparation for the upcoming workshop. The workshop invitees participated in the survey and submitted many risks encompassing all project phases and risk areas. The risk manager sorts risks by similarities and categories for the workshop. What should the risk manager do next to visually organize the risks?
Options
Q: 5
Members of a project team are not taking their risk management responsibilities seriously. They do not consider risk management as primary to the project’s success and do not believe that the benefits are significant. What should the risk manager do?
Options
Q: 6
In a large industrial business, an on-going system development project faces a previously identified risk. The risk is adequately managed by the risk manager, however there is still residual risk. What should the risk manager do?
Options
Q: 7
In a large enablement project with strict time lines, risks need to be closely monitored. The risk manager publishes reports comparing planned enablement sessions with actual enablement sessions, which help identify potential risks to be addressed. Which technique is the risk manager using?
Options
Q: 8
Product testing can be done in multiple ways. A few project team members suggest testing be done in a laboratory environment, whereas others recommend completing the analysis via simu-lation methods. The testing manager has consulted with a peer, who recommends undertaking testing using field trials. The testing manager consults with the risk manager to assess the risk involved in the testing. Which tool should the risk manager consider for assessing the test risk?
Options
Q: 9
A project team identifies that there is a probability of missing a key milestone in a project. The team wants to move forward with the risk response planning. What should the risk manager complete first?
Options
Q: 10
A project manager is working on a construction project. Based on past experience, the project manager identifies a risk that a supplier of a critical material may not deliver on time. The project manager has already accounted for this risk in the risk management plan. If this risk materializes, the project manager plans to procure the material from a different supplier. A potential risk in this plan is that there may be differences in the material provided by the first and second supplier. What type of risk is this?
Options
Q: 11
A risk management professional is in the process of categorizing risks when a subject matter expert (SME) suggests categorizing the risks by their impact to the project objectives. Why should the risk management professional use this approach?
Options
Q: 12
A project's design has been completed and approved on time. The construction subcontractor should be mobilizing to start construction but does not have the necessary materials in place, causing a delaying in the project. The risk register only contains risks for the design phase of the project. What should the project manager have done differently?
Options
Q: 13
A project team has completed the risk identification steps in a project and compiled a list of 25 risks. The team wants to create response plans for all the risks to avoid any future issues, but the resources and constraints limit the options. What should the risk manager do?
Options
Q: 14
An organization is embarking on a multi-million-dollar project with numerous identified risks. What should the project risk team do to navigate the risks on this project?
Options
Q: 15
After presenting a list of risks to the major project stakeholders and project sponsor, the board requested the risks be sorted differently from the results presented by the project team. This is a major issue and will cause a 2-week delay in the project. How could the risk manager have avoided the board's response?
Options
Q: 16
A risk manager on an infrastructure project gathers and analyzes performance dat a. The risk manager wants to identify which variables will impact the schedule and determine how these factors interact. Which data analysis tool should the risk manager use to forecast future performance?
Options
Q: 17
A budget change request was initiated by a functional manager in an organization due to a shortage in the functional manager's department budget. The functional manager asks the CEO to approve utilization of a contingency budget reserved for one of the projects in its closing phase. What should the risk manager of the related project have done to prevent this situation from happening?
Options
Q: 18
A new company initiates a project to incorporate a cybersecurity team. Which three documents should the risk manager analyze first? (Choose 3)
Options
Q: 19
A project manager was informed that the testing of the latest component in the project's software update release was not successful. As a result, 1he delivery timelines for the software release wifi be delayed, The project manager did not previously capture this as a risk to the project. What should the project manager do next to avoid similar risks?
Options
Q: 20
After a number of risk workshops, risks have been identified. Which is the first element the risk owner should look for in the response plan to help mitigate the risks?
Options
Question 1 of 20

Premium Access Includes

  • Quiz Simulator
  • Exam Mode
  • Progress Tracking
  • Question Saving
  • Flash Cards
  • Drag & Drops
  • 3 Months Access
  • PDF Downloads
Get Premium Access
Scroll to Top

FLASH OFFER

Days
Hours
Minutes
Seconds

avail 10% DISCOUNT on YOUR PURCHASE