Q: 1
A risk manager is facilitating a risk identification workshop on a new product with technical experts.
There is no consensus among the technical experts on most of the identified risks and their
characteristics. The risk manager decides to resolve this difference using another technique.
Which technique should the risk manager use in this situation?
Options
Discussion
No comments yet. Be the first to comment.
Be respectful. No spam.
Q: 2
The project team has correctly identified, assessed, and planned responses for a project's risks. The
risk manager is required to prepare a quarterly report on the performance of managing the risks.
What are two options the risk manager should consult for the analysis? (Choose two.)
Options
Discussion
No comments yet. Be the first to comment.
Be respectful. No spam.
Q: 3
A risk manager for a new product development project has worked diligently with stakeholders and
the project team to identify and document risks. These project risks vary widely in probability and
impact.
Which three actions should the risk manager take to inform the identification of resource
requirements for individual risk responses? (Choose 3).
Options
Discussion
No comments yet. Be the first to comment.
Be respectful. No spam.
Q: 4
A risk manager administered a pre-workshop risk survey in preparation for the upcoming workshop.
The workshop invitees participated in the survey and submitted many risks encompassing all project
phases and risk areas. The risk manager sorts risks by similarities and categories for the workshop.
What should the risk manager do next to visually organize the risks?
Options
Discussion
No comments yet. Be the first to comment.
Be respectful. No spam.
Q: 5
Members of a project team are not taking their risk management responsibilities seriously. They do
not consider risk management as primary to the project’s success and do not believe that the
benefits are significant.
What should the risk manager do?
Options
Discussion
No comments yet. Be the first to comment.
Be respectful. No spam.
Q: 6
In a large industrial business, an on-going system development project faces a previously identified
risk. The risk is adequately managed by the risk manager, however there is still residual risk.
What should the risk manager do?
Options
Discussion
No comments yet. Be the first to comment.
Be respectful. No spam.
Q: 7
In a large enablement project with strict time lines, risks need to be closely monitored. The risk
manager publishes reports comparing planned enablement sessions with actual enablement
sessions, which help identify potential risks to be addressed.
Which technique is the risk manager using?
Options
Discussion
No comments yet. Be the first to comment.
Be respectful. No spam.
Q: 8
Product testing can be done in multiple ways. A few project team members suggest testing be done
in a laboratory environment, whereas others recommend completing the analysis via simu-lation
methods. The testing manager has consulted with a peer, who recommends undertaking testing
using field trials. The testing manager consults with the risk manager to assess the risk involved in
the testing.
Which tool should the risk manager consider for assessing the test risk?
Options
Discussion
No comments yet. Be the first to comment.
Be respectful. No spam.
Q: 9
A project team identifies that there is a probability of missing a key milestone in a project. The team
wants to move forward with the risk response planning.
What should the risk manager complete first?
Options
Discussion
No comments yet. Be the first to comment.
Be respectful. No spam.
Q: 10
A project manager is working on a construction project. Based on past experience, the project
manager identifies a risk that a supplier of a critical material may not deliver on time. The project
manager has already accounted for this risk in the risk management plan. If this risk materializes, the
project manager plans to procure the material from a different supplier. A potential risk in this plan is
that there may be differences in the material provided by the first and second supplier.
What type of risk is this?
Options
Discussion
No comments yet. Be the first to comment.
Be respectful. No spam.
Q: 11
A risk management professional is in the process of categorizing risks when a subject matter expert
(SME) suggests categorizing the risks by their impact to the project objectives. Why should the risk
management professional use this approach?
Options
Discussion
No comments yet. Be the first to comment.
Be respectful. No spam.
Q: 12
A project's design has been completed and approved on time. The construction subcontractor should
be mobilizing to start construction but does not have the necessary materials in place, causing a
delaying in the project. The risk register only contains risks for the design phase of the project.
What should the project manager have done differently?
Options
Discussion
No comments yet. Be the first to comment.
Be respectful. No spam.
Q: 13
A project team has completed the risk identification steps in a project and compiled a list of 25 risks.
The team wants to create response plans for all the risks to avoid any future issues, but the resources
and constraints limit the options.
What should the risk manager do?
Options
Discussion
No comments yet. Be the first to comment.
Be respectful. No spam.
Q: 14
An organization is embarking on a multi-million-dollar project with numerous identified risks. What
should the project risk team do to navigate the risks on this project?
Options
Discussion
No comments yet. Be the first to comment.
Be respectful. No spam.
Q: 15
After presenting a list of risks to the major project stakeholders and project sponsor, the board
requested the risks be sorted differently from the results presented by the project team. This is a
major issue and will cause a 2-week delay in the project.
How could the risk manager have avoided the board's response?
Options
Discussion
No comments yet. Be the first to comment.
Be respectful. No spam.
Q: 16
A risk manager on an infrastructure project gathers and analyzes performance dat
a. The risk manager wants to identify which variables will impact the schedule and determine how
these factors interact.
Which data analysis tool should the risk manager use to forecast future performance?
Options
Discussion
No comments yet. Be the first to comment.
Be respectful. No spam.
Q: 17
A budget change request was initiated by a functional manager in an organization due to a shortage
in the functional manager's department budget. The functional manager asks the CEO to approve
utilization of a contingency budget reserved for one of the projects in its closing phase.
What should the risk manager of the related project have done to prevent this situation from
happening?
Options
Discussion
No comments yet. Be the first to comment.
Be respectful. No spam.
Q: 18
A new company initiates a project to incorporate a cybersecurity team. Which three documents
should the risk manager analyze first? (Choose 3)
Options
Discussion
No comments yet. Be the first to comment.
Be respectful. No spam.
Q: 19
A project manager was informed that the testing of the latest component in the project's software
update release was not successful. As a result, 1he delivery timelines for the software release wifi be
delayed, The project manager did not previously capture this as a risk to the project.
What should the project manager do next to avoid similar risks?
Options
Discussion
No comments yet. Be the first to comment.
Be respectful. No spam.
Q: 20
After a number of risk workshops, risks have been identified. Which is the first element the risk
owner should look for in the response plan to help mitigate the risks?
Options
Discussion
No comments yet. Be the first to comment.
Be respectful. No spam.