Free PK0-005 Practice Test Questions and Answers (2026)

Last Update Check
View Mode
Q: 1

SIMULATION During a gate review meeting, the deliverable was rejected by the customer. INSTRUCTIONS Review the dashboard. • Part 1: Drag and drop each task, placing them in the correct order based on the project change control process. • Part 2: Select the proper document(s) to be updated. If at any time you would like to bring back the initial state of the simulation, please click the Reset All button.

Drag & Drop
31 comments in the community discussion
6
Define new requirements, assess schedule/risk/cost, update and test, then demo. Update statement of work, schedule, change log. Pretty standard process.
6
Define new requirements and record changes → Assess schedule, risk, and cost → Update/test deliverable → Perform a demonstration. Docs: Statement of work, Schedule, Change log. Saw a similar question on a practice set, pretty sure that's the right flow. Risk register feels like a trap here if you're not careful.
Q: 2
Which of the following tools is best to use for storing lessons learned?
Options
31 comments in the community discussion
3
B . Wiki knowledge base is built for sharing info like lessons learned. Pretty straightforward pick in this scenario.
1
B here. Wiki knowledge bases let everyone update and find lessons learned fast, which is what the exam expects.
Q: 3
During the initiation phase, a stakeholder and the project manager discuss the business reasons and benefits of the project. The stakeholder requests these items be documented for approval. Which of the following should be used to document this information?
Options
32 comments in the community discussion
6
Makes sense to pick B here. The business case covers justification and benefits, not just scope stuff like A.
6
Option B here, since the business case lays out the justification and benefits before the work even starts. WBS is more for planning tasks, not capturing high-level value or reasons. I think that's the main trap. Agree?
Q: 4
Which of the following offers administrators more direct control over operating systems?
Options
22 comments in the community discussion
3
A . With Infrastructure as a Service (IaaS), admins get direct access to VMs, so you can configure and manage the operating system yourself. PaaS usually abstracts that layer away, only letting you work with runtimes or settings for your app. Unless they're asking about control at the app level, A should be right. Anyo
2
I don’t think B applies, A gives direct OS control. That’s typically what IaaS is for.
Q: 5
A program manager is reviewing the project portfolio and prioritizing each project based on the company's strategic plan. Which of the following should be considered in this evaluation? (Select TWO).
Options
40 comments in the community discussion
1
B. not A. Had something like this in a mock and the global environment was definitely one of the picks.
1
Don't think it's C. A and D are what you need for strategic alignment, plain and simple.
Q: 6
A project team gathers weekly to review its progress. Which of the following is the project manager MOST likely to have prepared to ensure team members who are absent remain informed about assignments?
Options
42 comments in the community discussion
4
D. not A. Meeting minutes are the standard way to capture who was assigned what during a meeting, while status reports usually miss the action items. Easy trap since status report sounds right if you ignore the assignments part. Seen this style on practice tests.
1
Had something like this in a mock. D
Q: 7
A PM received feedback from the project sponsor that the resources involved in the project are unsure of their daily activities. Which of the following is the MOST effective step for the PM to take to ensure clarity within the team?
Options
37 comments in the community discussion
5
Option C I saw a similar question in a recent exam review, and C lined up best for ongoing team clarity.
2
C here. Weekly Gantt chart reviews are what most official guides and practice tests suggest for ongoing team clarity.
Q: 8
A project manager has been very diligent in maintaining the version control for the documentation of requirements. Which of the following tools is the project manager using?
Options
34 comments in the community discussion
5
Option A. version control is really what makes multiauthoring software stand out here.
5
A. fits better for version control than a word processor. Tracking changes isn't enough.
Q: 9
A project implementation partner and the project manager disagree about completed requirements. The project manager shows the project requirements as 70% complete. The implementation partner validates that all requirements were completed. Which of the following would clarify what the project implementation partner was contractually expected to complete?
Options
40 comments in the community discussion
3
A. similar question showed up on a practice exam and SOW was the reference for contract obligations.
1
You'd want the SOW for this kind of dispute. That's what sets out what was contractually required, so A.
Q: 10
A project team is running into challenges because members are unclear about other members' roles. Which of the following charts should the project manager create?
Options
Question 1 of 20

Premium Access Includes

  • ✓Quiz Simulator
  • ✓Exam Mode
  • ✓Progress Tracking
  • ✓Question Saving
  • ✓Flash Cards
  • ✓Drag & Drops
  • ✓3 Months Access
  • ✓PDF Downloads
Get Premium Access
Scroll to Top