Q: 17

FILL IN THE BLANK Your project is in execution phase with a planned value of $500,000 and an earned value of $400,000. Your actual costs to date are $420,000. You need to calculate the cost performance index (CPI) to evaluate team efficiency and forecast project costs. What is the CPI?