NCARB PROJECT MANAGEMENT
Q: 1
What does “substantial completion” mean in the context of a construction contract?
Options
Discussion
No comments yet. Be the first to comment.
Be respectful. No spam.
Q: 2
In response to a request for qualifications for a prospective project, the architect assembles a project
team of mechanical, electrical, plumbing, and fire protection engineers.
What is the project?
Options
Discussion
No comments yet. Be the first to comment.
Be respectful. No spam.
Q: 3
According to AIA Document A201, who is responsible for obtaining permits and licenses required for
the project?
Options
Discussion
No comments yet. Be the first to comment.
Be respectful. No spam.
Q: 4
During the CD phase, it is discovered that the owner's food service consultant made a mistake that
results in the owner asking the architect to revise the design.
How should the architect proceed?
Options
Discussion
No comments yet. Be the first to comment.
Be respectful. No spam.
Q: 5
Which insurance policy protects the architect against claims of negligence?
Options
Discussion
No comments yet. Be the first to comment.
Be respectful. No spam.
Q: 6
What is the architect’s role regarding shop drawings?
Options
Discussion
No comments yet. Be the first to comment.
Be respectful. No spam.
Q: 7
What is the primary purpose of a construction schedule?
Options
Discussion
No comments yet. Be the first to comment.
Be respectful. No spam.
Q: 8
Which preliminary deliverables are usually provided for a schematic phase submission? Check the
four that apply.
Options
Discussion
No comments yet. Be the first to comment.
Be respectful. No spam.
Q: 9
An architecture firm has a C401 agreement with their consultants for a new design-bid-build
residential tower. The architect has approved a schedule provided by the mechanical engineer that
includes a two-week quality control review after each delivery milestone.
During the design development phase, the owner requests that the architect change the 8,000-
square-foot business center amenity for tenants to a private restaurant. The mechanical engineer
informs the architect that their schedule must be extended by four weeks to meet the owner's
request.
What should the architecture firm do first to maintain the start of construction?
Options
Discussion
No comments yet. Be the first to comment.
Be respectful. No spam.
Q: 10
After redesigning an existing restaurant, the architect submits the plans to the county for building
permit review. During the Zoning Review, the county requests the architect submit a site plan for
review and approval. After researching the county's records, the architect discovers a 40-year-old
approved site plan that is stamped, "Approval is based on the site plan and usage as indicated. Any
interior partitioning of the original building will be subject to review and approval by the county."
How should the architect proceed?
Options
Discussion
No comments yet. Be the first to comment.
Be respectful. No spam.
Q: 11
During the predesign phase of a project, the architect discovers that the owner's budget is
insufficient to meet the program requirements.
Which of the following should the architect do?
Options
Discussion
No comments yet. Be the first to comment.
Be respectful. No spam.
Q: 12
Near the end of a routine job site visit, the architect begins to assemble notes. The owner's
representative then arrives on site unexpectedly. The architect, owner's representative, and
contractor discuss and resolve several outstanding project issues. The architect begins writing
correspondence to distribute to the project team when the architect returns to the office.
In addition to a Meeting Record, which of the following documents should the architect create?
Options
Discussion
No comments yet. Be the first to comment.
Be respectful. No spam.
Q: 13
Refer to the exhibit.
In the chart shown, what is typically a part of the "Bidding Documents"?
In the chart shown, what is typically a part of the "Bidding Documents"?Options
Discussion
No comments yet. Be the first to comment.
Be respectful. No spam.
Q: 14
A project is being delivered by Integrated Project Delivery (IPD). The architect is developing the
internal budget.
Which of the following should require less staff time?
Options
Discussion
No comments yet. Be the first to comment.
Be respectful. No spam.
Q: 15
A new restaurant design must incorporate specific light fixtures to meet the franchise requirements.
The owner conveys this to the architect, who must make sure that prospective bidders do not
overlook specific fixtures.
Which method should the architect use during the construction documents phase?
Options
Discussion
No comments yet. Be the first to comment.
Be respectful. No spam.