According to the Applying Lean Estimating and Forecasting in Cadence article on the Scaled Agile
Framework website, ART velocities are used to conduct ‘what if’ analysis for estimating and
forecasting in SAFe. The article states that “The ART velocity is used to conduct ‘what if’ analysis,
which helps determine the feasibility of the plan and the number of features that can be delivered in
a PI. The ART velocity is also used to forecast the delivery of features and capabilities beyond the
current PI.” Therefore, the correct answer is C, ART velocities are used to conduct ‘what if’ analysis.
The other options are not accurate, as they are not the statements that are true for estimating and
forecasting in SAFe. Feature estimation is not independent of team-level input (A), as teams are
involved in estimating the size and complexity of features using story points or normalized story
points. Epics are not estimated by the Epic Owner (B), as they are estimated collaboratively by the
Epic Owner, Enterprise Architect, and Lean Portfolio Management. Work breakdown structure to the
task level does not help increase estimation accuracy (D), as it introduces unnecessary overhead and
delays feedback.