Q: 34

A project manager works for a communications company. The manager of the mobile equipment department is concerned about the current project's activities. According to the current project management plan, the department will need to purchase special equipment, but the cost was not planned. The project sponsor insists the project should move forward because customers will be impacted if the equipment is not available. What should the project manager do?

Options