Q: 32
A product owner who possesses a strong technical background has been actively involved with the project team for several years. The product owner has been quite vocal about the expected duration of the work. As a result, the project team has ceased providing development estimates to avoid causing any dissatisfaction with the product owner. What should the project manager do?