During execution, your team uncovers a technical risk that could require significant rework if it materializes. A senior engineer proposes a preventive solution that would add 80 hours of effort now, reducing the probability of the risk from 60% down to 15%. The sponsor's budget is tight, and she has asked you not to add scope without her explicit approval. However, waiting to see if the risk occurs could result in 400 hours of rework plus schedule delay. What should you do?