Q: 11
A business analyst is discussing the acceptance criteria for a new measurement system with the operations manager. The operations manager is particularly concerned about the accuracy of the new system because mistakes in data measurements could be extremely costly to fix. Which of the following is the best strategy to define the appropriate acceptance criteria?
Options
Q: 12
A business analyst needs to estimate the effort associated with project requirements. However, the lack of detail is concerning. What technique could the business analyst use to help alleviate this concern?
Options
Q: 13
How should a business analyst determine whether a solution satisfies business requirements?
Options
Q: 14
A major stakeholder of a project is surprised to learn that a particular requirement was not implemented during the latest launch. The business analyst tells the stakeholder that the requirement status was changed to "deferred ” What could have prevented the stakeholder from being surprised about the status change?
Options
Q: 15
When eliciting requirements, a good time to consider using the interviewing method is when:
Options
Q: 16
The stakeholders for a newly approved project are subject matter experts who are very knowledgeable in the client's business and will provide the project requirements. The project team scheduled separate sessions with each subject matter expert to identify and prioritize the requirements. Which technique is being used?
Options
Q: 17
A few months into a project, the business analyst determines that the costs are exceeding the perceived benefits. The business analyst wants to address the possible risks of having to cancel the product. Which of the following documents should be used?
Options
Q: 18
A business analyst is planning the business analysis activities for a new payroll project. Due to a tight timeline, the analyst advises stakeholders that the requirements sessions should begin as soon as possible. Which key factor drives the selection of business analyst activities to be included in the project?
Options
Q: 19
Company A is working on implementing a new platform with multiple stakeholders. The business analyst has gathered the requirements and established a baseline. However, scope creep is a persistent problem. What could the business analyst have established to help manage this situation?
Options
Q: 20
A business analyst is trying to complete the requirement documentation of a project and finds that the developers have started development. The business analyst should first facilitate the:
Options
Question 11 of 20 · Page 2 / 2

Premium Access Includes

  • Quiz Simulator
  • Exam Mode
  • Progress Tracking
  • Question Saving
  • Flash Cards
  • Drag & Drops
  • 3 Months Access
  • PDF Downloads
Get Premium Access
Scroll to Top

FLASH OFFER

Days
Hours
Minutes
Seconds

avail 10% DISCOUNT on YOUR PURCHASE