View Mode
Q: 1
You configure a service level to adjust assignment urgency to 100 when the goal interval lapses. What does the assignment urgency impact the deadline and passed deadline intervals?
Options
Question 1 of 10

Premium Access Includes

  • Quiz Simulator
  • Exam Mode
  • Progress Tracking
  • Question Saving
  • Flash Cards
  • Drag & Drops
  • 3 Months Access
  • PDF Downloads
Get Premium Access
Scroll to Top

FLASH OFFER

Days
Hours
Minutes
Seconds

avail 10% DISCOUNT on YOUR PURCHASE