Consider this scenario.
A new Expense Report is submitted and must be reviewed. The assignment urgency and the initial
urgency values are both set to 10.
The SLA starts when the assignment is created
If the goal elapses and the assignment is not yet completed, the assignment urgency is increase by
10
If the deadline elapses and the assignment is not yet completed, the assignment urgency increases
by 10
If the passed deadline elapses and the assignment is not yet competed, the assignment urgency
increases by 10
In the Answer Area, select the urgency for each milestone.