Q: 16
[Apply Deployment Management Processes] An organization is deploying new software and new servers to support a service that will be launched soon. Which TWO of these activities should the organization conduct as part of the 'verification of the service components' activity of the 'deployment lifecycle management' process? Checking that the correct models of server have been supplied Testing the software for defects Creating a schedule for installing the new servers Installing the new software to the newly installed servers
Options