Q: 18
What is the purpose of test completion criteria in a test plan:
Options
Discussion
Option E
Option E is correct here. Test completion criteria in the test plan specifically help define when you can stop testing the whole system, not just single test cases. A is a trap since that's about individual tests finishing, not the project. I think ISTQB is pretty consistent about this.
Definitely E. The completion criteria are meant to help you decide when testing is done for the project as a whole, not just an individual case. Saw a similar question in practice sets. Pretty sure this is what ISTQB means by when to stop testing-agree?
So tired of ISTQB nitpicking this stuff. E imo, test completion criteria tell you when to stop testing overall, not just mark a single test complete. Pretty sure that's what the syllabus wants, unless they're being extra tricky.