Q: 4
A manager has not yet used all oh his budget. He is worried that his budget maybe reduced next year
if he is not seen to have needed all the funds. He decides to spend the remaining £1,580 on another
team building exercise as well as a catered lunch for his department.
This example falls under which behavioural aspect of budgetary control?
Options