Q: 1
After winning a large government contract, a company needs to hire a portfolio manager What vital
qualification should candidates possess?
Options
Discussion
C isn't right for portfolio manager. Should be A since portfolio management is all about handling strategic alignment across multiple projects, not just coordinating or balancing them. Pretty sure about this but let me know if you see it differently.
Guessing C-seen a similar question in the official guide and practice exams.
Be respectful. No spam.
Q: 2
Ensuring that both parties meet contractual obligations and that their own legal rights are protected
is a function of:
Options
Discussion
C tbh
Be respectful. No spam.
Q: 3
An input of the Plan Procurement Management process is:
Options
Discussion
Option B Official guide and practice tests both confirm activity cost estimates as an input here.
B that's what's listed as an input to Plan Procurement in the guide. Proposals and docs are outputs or come later.
B tbh, makes sense since you need estimates before figuring out what to procure. PMBOK lists activity cost estimates as an input here, even if they're not final. The others (like proposals/docs) come later. Pretty sure B is right but open to other takes.
Wouldn't it depend if the cost estimates are finalized yet? Sometimes early in planning, you might only have rough figures, but PMBOK still calls for activity cost estimates as the input here.
Be respectful. No spam.
Q: 4
Definitions of probability and impact, revised stakeholder tolerances, and tracking are components of
which subsidiary plan?
Options
Discussion
Pretty sure it's D, had something like this on a mock before. Risk management plan covers probability, impact definitions, stakeholder tolerance, and how risks will be tracked. The other plans don't really address those pieces.
Be respectful. No spam.
Q: 5
What is the probability of occurrence if the risk rating is 0.56 and the impact if the risk does occur is
very high (0.80)?
Options
Discussion
C , B is a common trap if you confuse rating with probability.
C
I’d say B-I thought risk rating and probability could be the same here. I figured 0.56 was just given directly as the probability, since that matches the risk rating they provided. Not sure if I'm missing a calculation step though.
Its C. Probability is risk rating divided by impact, so 0.56 / 0.80 equals 0.70. B looks tempting since it matches the risk rating, but that's not asked for here. Open to corrections if I missed something.
C vs B here, but pretty sure it's C. Used the risk formula (risk rating divided by impact) and that gives 0.70. Seen similar logic in official guide and some practice tests.
Be respectful. No spam.
Q: 6
The iterative and interactive nature of the Process Groups creates the need for the processes in
which Knowledge Area?
Options
Discussion
Don't think it's C, that's a common trap since risk is also iterative but integration is really what connects all process groups.
C tbh
Be respectful. No spam.
Q: 7
The ways in which the roles and responsibilities, reporting relationships, and staffing management
will be addressed and structured within a project is described in the:
Options
Discussion
Option A, I think? Roles and reporting lines sound like human resource plan stuff. Can someone confirm?
Be respectful. No spam.
Q: 8
Which Control Quality tool is also known as an arrow diagram?
Options
Discussion
C/D? It's D, activity network diagram is the arrow diagram here. Tree diagram mixes up a lot of folks though.
Yeah, this one trips people up but it's D. The activity network diagram uses arrows to show dependencies and order of tasks, which is why it's called an arrow diagram in PMI lingo. Tree diagrams are for hierarchical structures, not sequences. Pretty sure on this, but correct me if I'm missing something.
These PMI naming conventions drive me nuts, but it’s D.
This looks like one from my exam last year on my last exam, it's D.
C/D? Never sure if it's tree or activity network diagram, think D this time. Someone confirm?
Be respectful. No spam.
Q: 9
When a permitting agency takes longer than planned to issue a permit, this can be described as a
risk:
Options
Discussion
A, This matches PMI's terminology, since the delay actually happening is a risk event not just a perception or impact.
D , since the delay actually affects the project outcomes, it's the impact of the risk. The event is more about the thing happening, but here I think PMI might call the result an impact. Not totally sure though-these terms get mixed up a lot.
A for me. If the delay actually happens, in PMI talk that's a risk event. The other choices don't really fit. Disagree?
Be respectful. No spam.
Q: 10
A project manager seeking insight on previous stakeholder management plans and their
effectiveness should evaluate:
Options
Discussion
Yeah, I'd pick A here. The lessons-learned database covers what went well or not, and historical info gives the actual plans. B doesn't really give you the effectiveness piece. Pretty sure A's the way to go.
A imo. Historical info plus the lessons-learned database directly show what worked or didn't in past stakeholder management, unlike just the register from B. Similar question tripped me up since stakeholder register alone misses effectiveness context.
Be respectful. No spam.
Question 1 of 20 · Page 1 / 2