Q: 3
An input of the Plan Procurement Management process is:
Options
Discussion
Option B Official guide and practice tests both confirm activity cost estimates as an input here.
Option B, official guide lists activity cost estimates as input and I've seen this called out in some practice sets too.
Makes sense to pick B here. Activity cost estimates are used during planning, the rest are outputs or later stage artifacts.
B not D. Trap here is thinking procurement documents are inputs, but they're actually outputs later on. Activity cost estimates feed into the planning up front-pretty sure that's what PMI expects.
Had something like this in a mock and it was definitely B. Activity cost estimates come in as an input because you need to know the potential costs before planning procurement activities. The other options are outputs or later in the process flow I think. Let me know if anyone disagrees, but I'm pretty confident here.
Yeah I think it's still B since activity cost estimates are used up front here.
B , that's what's in the official guide and I saw similar in practice exam sets too.
B , not A since make-or-buy is actually a tool here not an input.
B that's what's listed as an input to Plan Procurement in the guide. Proposals and docs are outputs or come later.
B tbh, makes sense since you need estimates before figuring out what to procure. PMBOK lists activity cost estimates as an input here, even if they're not final. The others (like proposals/docs) come later. Pretty sure B is right but open to other takes.
Be respectful. No spam.