Q: 20
DRAG DROP Match each tool or technique with its corresponding Project Cost Management process.
Drag & Drop
Discussion
Decision making → Plan Cost Management, TCPI → Control Costs, Meetings → Determine Budget, Historical info review → Estimate Costs. Saw a nearly identical mapping on a practice set and it lines up with how these tools fit each cost process per PMBOK. Pretty sure some might mix up Meetings or Decision making since those show up in multiple processes, but this looks right for this exact question. Agree?
Not sure I agree with the usual matches. I put Decision making with Control Costs, TCPI under Plan Cost Management, Meetings for Estimate Costs, and Historical review to Determine Budget. Maybe I'm mixing up the order but I thought TCPI comes up during planning. Anyone else seeing it this way?
Yeah, that’s right. Decision making to Plan Cost Management, TCPI to Control Costs, Meetings for Determine Budget, Historical info review for Estimate Costs.
Man, PMI always mixes me up with these. I matched Decision making to Control Costs, TCPI to Plan Cost Management, Meetings to Estimate Costs, and Historical information review to Determine Budget.