Q: 18
The Salesforce delivery team at Cloud Kicks consistently has user stories that developers start but are unable to complete during each sprint. During the most recent retrospective, the development team expressed that they are running out of time to complete the stories. The team used the INVEST checklist to diagnose why these stories are incomplete at the end of the sprint. Which checklist item is the most likely reason why the stories are incomplete at the close of the sprint?
Options
Question 18 of 35