Q: 11
A chart showing the trend in the lag time from defect reporting to resolution during system testing is
also available. The chart shows that the daily closure period is consistently and significantly above
the rolling closure period for a long period of the system testing phase. Almost all defects found
during system testing have been related to the system as a whole, not related to single units or
integrations issues. Almost all quality risks have been addressed during the unit and integration
testing phase and no residual quality risks were present in the integrated system. This has been
confirmed by exploratory testing sessions performed during system testing, targeted at finding
defects in these quality risk areas. Based on the given information only, which one of the following
areas would you expect to be considered more in the retrospective meeting in order to be improved?
K3 3 credits