Q: 18
An IT team plans to deploy a new service built on top of an existing service. The capacity needed for
the new service is difficult to estimate because the demand for the new service is undetermined. The
team has these deployment requirements:
• A subset of the users of the original service must be migrated to the new service based on their
profile
• The new service must be rolled back easily if capacity exceeds estimates
Which deployment strategy must be used?