Q: 10

You have four resources in your organization: P, Q, R, and S. Resource P – Project or resource calendar is active. Resource Q – Project resource request dates are within the project or resource calendar effective dates. Resource R – Resource calendar is complex, it does not contain seven days, and it contains more than one pattern and shift. Resource S – Number of working days within the requested date range is not zero on the project or resource calendar. Identify the resource for whom Resource Availability Capacity Score will not be calculated. (Choose the best

Options
Question 10 of 25