You are not confident with the assessment of the risk level and you suspect that it will be possible to find high-priority bugs in low-risk areas. Furthermore the period for test execution is very short. Your goal is to test all the product risks in a risk-based way, while assuring that each product risk gets at least some amount of testing.
Which of the following answers describes the best test execution schedule in this scenario? Number of correct responses: 1
You are following a risk-based testing strategy. The test execution time is very limited. Assume that all the product risk items require more or less the same level of test effort.
Which of the following answers describes the best execution schedule in this scenario? Number of correct responses: 1
Assume that the following test cases have been executed at the end of the first week of test execution: TC-001, TC-002 and TC-007. All these tests are ‘passes’. What is the MINIMUM number of the remaining test cases that must be successfully executed to fulfill the EX1 exit criteria?
Number of correct responses: 1