Q: 1

SIMULATION During a gate review meeting, the deliverable was rejected by the customer. INSTRUCTIONS Review the dashboard. • Part 1: Drag and drop each task, placing them in the correct order based on the project change control process. • Part 2: Select the proper document(s) to be updated. If at any time you would like to bring back the initial state of the simulation, please click the Reset All button.

Drag & Drop
31 comments in the community discussion
6
Define new requirements, assess schedule/risk/cost, update and test, then demo. Update statement of work, schedule, change log. Pretty standard process.
6
Define new requirements and record changes → Assess schedule, risk, and cost → Update/test deliverable → Perform a demonstration. Docs: Statement of work, Schedule, Change log. Saw a similar question on a practice set, pretty sure that's the right flow. Risk register feels like a trap here if you're not careful.
Q: 2
Which of the following tools is best to use for storing lessons learned?
Options
31 comments in the community discussion
3
B . Wiki knowledge base is built for sharing info like lessons learned. Pretty straightforward pick in this scenario.
1
B here. Wiki knowledge bases let everyone update and find lessons learned fast, which is what the exam expects.
Q: 3
During the initiation phase, a stakeholder and the project manager discuss the business reasons and benefits of the project. The stakeholder requests these items be documented for approval. Which of the following should be used to document this information?
Options
32 comments in the community discussion
6
Makes sense to pick B here. The business case covers justification and benefits, not just scope stuff like A.
6
Option B here, since the business case lays out the justification and benefits before the work even starts. WBS is more for planning tasks, not capturing high-level value or reasons. I think that's the main trap. Agree?
Q: 4
Which of the following offers administrators more direct control over operating systems?
Options
22 comments in the community discussion
3
A . With Infrastructure as a Service (IaaS), admins get direct access to VMs, so you can configure and manage the operating system yourself. PaaS usually abstracts that layer away, only letting you work with runtimes or settings for your app. Unless they're asking about control at the app level, A should be right. Anyo
2
I don’t think B applies, A gives direct OS control. That’s typically what IaaS is for.
Q: 5
A program manager is reviewing the project portfolio and prioritizing each project based on the company's strategic plan. Which of the following should be considered in this evaluation? (Select TWO).
Options
40 comments in the community discussion
1
B. not A. Had something like this in a mock and the global environment was definitely one of the picks.
1
Don't think it's C. A and D are what you need for strategic alignment, plain and simple.
Q: 6
A project team gathers weekly to review its progress. Which of the following is the project manager MOST likely to have prepared to ensure team members who are absent remain informed about assignments?
Options
42 comments in the community discussion
4
D. not A. Meeting minutes are the standard way to capture who was assigned what during a meeting, while status reports usually miss the action items. Easy trap since status report sounds right if you ignore the assignments part. Seen this style on practice tests.
1
Had something like this in a mock. D
Q: 7
A PM received feedback from the project sponsor that the resources involved in the project are unsure of their daily activities. Which of the following is the MOST effective step for the PM to take to ensure clarity within the team?
Options
37 comments in the community discussion
5
Option C I saw a similar question in a recent exam review, and C lined up best for ongoing team clarity.
2
C here. Weekly Gantt chart reviews are what most official guides and practice tests suggest for ongoing team clarity.
Q: 8
A project manager has been very diligent in maintaining the version control for the documentation of requirements. Which of the following tools is the project manager using?
Options
34 comments in the community discussion
5
Option A. version control is really what makes multiauthoring software stand out here.
5
A. fits better for version control than a word processor. Tracking changes isn't enough.
Q: 9
A project implementation partner and the project manager disagree about completed requirements. The project manager shows the project requirements as 70% complete. The implementation partner validates that all requirements were completed. Which of the following would clarify what the project implementation partner was contractually expected to complete?
Options
40 comments in the community discussion
3
A. similar question showed up on a practice exam and SOW was the reference for contract obligations.
1
You'd want the SOW for this kind of dispute. That's what sets out what was contractually required, so A.
Q: 10
Given the following information: CompTIA Project+ PK0-005 question Which of the following represents the critical path of the project?
Options
39 comments in the community discussion
4
Option C
4
Option C but if D had one extra day on E it would flip to D as the critical path.
Q: 11
A customer requests some changes to a product, and those changes are approved by the CCB. Which of the following should be changed first?
Options
9 comments in the community discussion
3
D. but if the scope wasn’t impacted would the SOW still change first or something else?
1
D
Q: 12
While managing a project, a PM is assigned to work on a second project. The second project becomes more complex and monopolizes the PM's time. The PM learns that a similarly time- consuming project was executed previously in the organization. Which of the following actions should the PM take?
Options
17 comments in the community discussion
1
Official study guide and practice test both mention D.
1
Feeling a bit lost on this one, but I think it's D. Can someone confirm if the PMO is usually the right call here?
Q: 13
A project team is working on a document to precisely describe the success criteria that should be fulfilled by a product. Which of the following documents is the team preparing?
Options
11 comments in the community discussion
2
I don't think it's B. Quality plan is about how quality will be managed, but "success criteria" means what the product must achieve, and that's covered by the project scope (A). I've seen similar questions on practice exams where B is a common trap.
1
A
Q: 14
SIMULATION During the project execution phase, Ann, a project manager, received an email from the project sponsor asking for an additional work package to be added to the project scope due to new legislation. INSTRUCTIONS Review the email with the latest updates sent by the project sponsor and respond in the following order: 1. Select the best tool for tracking the server migration progress. 2. Select the new critical path. 3. Select the correct number of engineers required for the server migration phase. If at any time you would like to bring back the initial state of the simulation, please click the Reset All button. CompTIA Project+ PK0-005 question Select the Appropriate Tool: CompTIA Project+ PK0-005 question CompTIA Project+ PK0-005 question CompTIA Project+ PK0-005 question CompTIA Project+ PK0-005 question CompTIA Project+ PK0-005 question Select the new critical path. Option A CompTIA Project+ PK0-005 question Option B CompTIA Project+ PK0-005 question Option C CompTIA Project+ PK0-005 question CompTIA Project+ PK0-005 question
Your Answer
6 comments in the community discussion
6
Saw a similar sim in practice. Official exam book and hands-on labs cover these scope/change control flows pretty well.
6
SEE THE
Q: 15
A PM wants to add a chart to the monthly status report to show major accomplishments for key events. Which of the following is the best chart to use?
Options
9 comments in the community discussion
2
A . Official guide and some practice tests always say milestone charts are best for this.
2
Option A, super clear question layout here.
Q: 16
A company asks some vendors to provide a solution for its specific needs. Which of the following documents should the company provide?
Options
10 comments in the community discussion
1
Heard something similar shows up a lot, leaning A but not totally sure.
Pretty sure similar question appeared on my practice test, it's A.
Q: 17
Which of the following is a typical characteristic of Scrum?
Options
9 comments in the community discussion
1
Pretty sure it's C, self-organized team fits Scrum from what I remember. Agree?
C , self-organized teams are a big part of Scrum methodology. The team decides how to get work done within each sprint instead of being micromanaged. Saw a similar question in an exam report and C was the consensus. Pretty sure that’s what CompTIA is looking for here, but open to other takes.
Q: 18
Government projects require that personnel submit to background screenings for certain clearance requirements. Which of the following best describes this process?
Options
8 comments in the community discussion
6
B . Operational security is the one that deals with personnel screening and clearances, not just tech or door locks.
1
C vs B? I picked C since background checks kinda feel like physical security with badges, but could be missing something here.
Q: 19
During the execution phase of a project, team members have been constantly disagreeing about the tasks they have been assigned. Which of the following is most likely the reason they are disagreeing?
Options
10 comments in the community discussion
6
Option B
1
B , goes with what the official guide and practice questions suggest for RACI issues.
Q: 20
During the project execution, the sponsor would like to have a visual representation indicating the progress of the project The project is being managed using agile methodologies Which of the following tools would best help the sponsor with the request?
Options
13 comments in the community discussion
2
Yeah I agree with D.
1
B makes sense to me, since velocity charts track how much work is completed each iteration. In agile, teams often use velocity to gauge progress, right? Not totally sure though if that's what the sponsor wants visually.
Question 1 of 20

Premium Access Includes

  • Quiz Simulator
  • Exam Mode
  • Progress Tracking
  • Question Saving
  • Flash Cards
  • Drag & Drops
  • 3 Months Access
  • PDF Downloads
Get Premium Access
Scroll to Top

FLASH OFFER

Days
Hours
Minutes
Seconds

avail 10% DISCOUNT on YOUR PURCHASE