Q: 1
Two team members are assigned to a task that is expected to start this Tuesday based on the predecessor and the task constraint, but the Planned Start Date is showing as this Friday. Why may this be the case?
Options
Q: 2
A company has decided that all projects for the year need to be created from templates and staffed in the following quarter. The projects will need to remain in a backlog until the team has capacity to work on them. There has been confusion previously because the team used Planning status for all work not started. What should the project manager do to help the team see the difference between work in the backlog versus work that is now being planned?
Options
Q: 3
Which date type should an assignee update to change the completion date of a task?
Options
Q: 4
How is the primary assignee of a task determined?
Options
Q: 5
A task was originally planned with a 10-day duration and 40 planned hours. The client needs it done in 3 days. What task setting needs to change to allow 4 users to complete this in less than 3 days?
Options
Q: 6
What are two ways to associate milestone steps to tasks? (Choose two.)
Options
Q: 7
The marketing team should begin working on a task on September 23, complete it within 2 weeks and take approximately 10 hours over that time span to execute the deliverable. Which task settings need to be configured to meet these requirements?
Options
Q: 8
What parent object can have child objects?
Options
Q: 9
Which project status defaults the project condition to On Target?
Options
Q: 10
A project manager would like to see the Budgeted Variances between the hours for the current week. Where is that information found at the project level?
Options
Q: 11
The executive team at Company A has asked the Workfront System Administrator how they can get visibility into the health, importance, and strategic alignment of active projects across the organization so that they can quickly make data-driven business decisions. Which report grants the executive team this visibility?
Options
Q: 12
All of the tasks on a project show as 100% complete, but when the Project Owner tries to update the status of the project to Complete, the Owner receives an error that reads "Project cannot be marked Complete if there are open issues and tasks that are not complete." How can the Project Owner determine which tasks are incomplete?
Options
Q: 13
An executive wants to see the actual cost of projects within a selected portfolio, allowing for multiple reports with the option to select a specific portfolio, sorted in a descending order, so the most expensive projects appear on top. Which steps should be taken to create this report?
Options
Q: 14
A project manager has been asked to create a report showing the planned completion date for all the project manager's projects. The report must show results in a calendar view and all entries should be purple. What steps should the project manager take to create this view?
Options
Q: 15
Which wildcard should be used on a project report when filtering for projects that have a planned completion date greater than 1 month from the current date?
Options
Question 1 of 20

Premium Access Includes

  • Quiz Simulator
  • Exam Mode
  • Progress Tracking
  • Question Saving
  • Flash Cards
  • Drag & Drops
  • 3 Months Access
  • PDF Downloads
Get Premium Access
Scroll to Top

FLASH OFFER

Days
Hours
Minutes
Seconds

avail 10% DISCOUNT on YOUR PURCHASE