Free AD0-E903 Practice Test Questions and Answers (2026) | Cert Empire Practice Questions
Free preview: 20 questions.
Adobe AD0 E903
Q: 1
Two team members are assigned to a task that is expected to start this Tuesday based on the
predecessor and the task constraint, but the Planned Start Date is showing as this Friday.
Why may this be the case?
Options
Discussion
No comments yet. Be the first to comment.
Be respectful. No spam.
Q: 2
A company has decided that all projects for the year need to be created from templates and staffed
in the following quarter. The projects will need to remain in a backlog until the team has capacity to
work on them. There has been confusion previously because the team used Planning status for all
work not started.
What should the project manager do to help the team see the difference between work in the
backlog versus work that is now being planned?
Options
Discussion
No comments yet. Be the first to comment.
Be respectful. No spam.
Q: 3
Which date type should an assignee update to change the completion date of a task?
Options
Discussion
No comments yet. Be the first to comment.
Be respectful. No spam.
Q: 4
How is the primary assignee of a task determined?
Options
Discussion
No comments yet. Be the first to comment.
Be respectful. No spam.
Q: 5
A task was originally planned with a 10-day duration and 40 planned hours. The client needs it done
in 3 days.
What task setting needs to change to allow 4 users to complete this in less than 3 days?
Options
Discussion
No comments yet. Be the first to comment.
Be respectful. No spam.
Q: 6
What are two ways to associate milestone steps to tasks? (Choose two.)
Options
Discussion
No comments yet. Be the first to comment.
Be respectful. No spam.
Q: 7
The marketing team should begin working on a task on September 23, complete it within 2 weeks
and take approximately 10 hours over that time span to execute the deliverable.
Which task settings need to be configured to meet these requirements?
Options
Discussion
No comments yet. Be the first to comment.
Be respectful. No spam.
Q: 8
What parent object can have child objects?
Options
Discussion
No comments yet. Be the first to comment.
Be respectful. No spam.
Q: 9
Which project status defaults the project condition to On Target?
Options
Discussion
No comments yet. Be the first to comment.
Be respectful. No spam.
Q: 10
A project manager would like to see the Budgeted Variances between the hours for the current
week. Where is that information found at the project level?
Options
Discussion
No comments yet. Be the first to comment.
Be respectful. No spam.
Q: 11
The executive team at Company A has asked the Workfront System Administrator how they can get
visibility into the health, importance, and strategic alignment of active projects across the
organization so that they can quickly make data-driven business decisions.
Which report grants the executive team this visibility?
Options
Discussion
No comments yet. Be the first to comment.
Be respectful. No spam.
Q: 12
All of the tasks on a project show as 100% complete, but when the Project Owner tries to update the
status of the project to Complete, the Owner receives an error that reads "Project cannot be marked
Complete if there are open issues and tasks that are not complete." How can the Project Owner
determine which tasks are incomplete?
Options
Discussion
No comments yet. Be the first to comment.
Be respectful. No spam.
Q: 13
An executive wants to see the actual cost of projects within a selected portfolio, allowing for multiple
reports with the option to select a specific portfolio, sorted in a descending order, so the most
expensive projects appear on top. Which steps should be taken to create this report?
Options
Discussion
No comments yet. Be the first to comment.
Be respectful. No spam.
Q: 14
A project manager has been asked to create a report showing the planned completion date for all the
project manager's projects. The report must show results in a calendar view and all entries should be
purple. What steps should the project manager take to create this view?
Options
Discussion
No comments yet. Be the first to comment.
Be respectful. No spam.
Q: 15
Which wildcard should be used on a project report when filtering for projects that have a planned
completion date greater than 1 month from the current date?
Options
Discussion
No comments yet. Be the first to comment.
Be respectful. No spam.
Question 1 of 20