1Z0-511.pdf
Q: 1
Your company wants to define all its equipments as Non-Labor resources to track the cost incurred on
the usage of these equipments, when defining the equipment. When defining the equipment as a
Non-Labor resource in the system, you need to assign an expenditure type to it. What kind of
expenditure type to it. What kind of expenditure type can be assigned to a Non-Labor resource?
Options
Q: 2
The Profile option "PA: Cross Project User-Update" is set to "Yes" for a Projects module user. Which
two statements apply?
Options
Q: 3
An organization wants to consolidate work based billing across multiple projects (produce one
invoice for a single customer based on multiple contract projects). Which two methods will help
them accomplish this?
Options
Q: 4
A customer has gone into bankruptcy and is unable to pay their bills. This means that the project
revenue is now overstated. How can the customer reduce the revenue on the project to accurately
reflect the amount of collectable revenue?
Options
Q: 5
A project manager wants to create a revenue budget based on the project agreement and allocated
funding. How can this be achieved?
Options
Q: 6
What must be defined to enable a company to use an organization for a straight time expenditure?
Options
Q: 7
Your company has set up the burdening functionality to capture the overheads incurred on all
projects. They have decided to store these overhead costs as a separate expenditure item on the
same project and also charge it to a separate expense account. Which step would you perform to set
up the required expense account?
Options
Q: 8
You have imported Labor transactions into Oracle Projects from Oracle Time and Labor by running
the "PRC: Transaction Import" program. What is the correct sequence to run the concurrent
programs listed below to transfer the cost and accounting entries of these transactions to General
Ledger?
1. PRC: Distribute Labor Cost
2.PRC: Transfer Journal Entries to GL
3.PRC: Create Accounting (with the Transfer to GL option set to "No")
4.PRC: Interface Labor Costs to GL
5.PRC: Generate Cost Accounting Events
6.PRC: Distribute and Interface tabor costs to GL
Options
Q: 9
A customer enables transaction controls at the Project level. Oracle Project Costing checks the
control when the customer ________.
Options
Q: 10
In which two circumstances would it be appropriate to deselect the "Interface Revenue to GL" option
in System Implementation Options, before you run the Interface to GC?
Options
Question 1 of 10