Q: 2
The planning for NEWGEN has started
-
ZYXS will be the service integrator
-
OUTSCO will provide application support services
-
NETSCO will provide network services.
-
PAYSCO is asked to continue to provide payroll services
Users are happy with the services of PAYSCO The contract with PAYSCO has 2 years left to run This is
18 months after the expected completion date ot the implementation of the SIAM model Initial
discussions by ZYXS with PAYSCO have indicated that PAYSCO does not want to make any contract
changes to support the SIAM model.
Given this constraint what is most likely to be the best method to plan for onboarding PAYSCO?