During the final plan review of the Program Increment (PI) Planning, the teams cover several critical
pieces of information. This includes any changes to team capacity and load, which may affect the
delivery of PI Objectives. The final PI Objectives are reviewed to ensure alignment with the ART’s
goals. Additionally, ART PI Risks are addressed, including any new risks identified during the planning
process, and existing risks that have been ROAMed (Resolved, Owned, Accepted, Mitigated). Lastly,
any impediments that could hinder the ART’s progress are discussed, ensuring that they are
acknowledged and addressed appropriately. This comprehensive review is essential for the ART to
commit to a set of PI Objectives that are achievable and aligned with the overall strategy1.