1. Schwaber
K.
& Sutherland
J. (2020). The Scrum Guide. Scrum.org.
Page 9
"Definition of Done" section: "The Definition of Done is a formal description of the state of the Increment when it meets the quality measures required for the product. ... If a Product Backlog item does not meet the Definition of Done
it cannot be released or even presented at the Sprint Review."
Page 8
"Sprint Planning" section: "The Developers are responsible for all quality-adhering work needed to create a Done Increment."
2. Verwijs
C.
& Russo
D. (2022). A Theory of Scrum. Zenodo. https://doi.org/10.5281/zenodo.7264986
Page 11
Section 3.3.3
"Definition of Done": "The Definition of Done is a commitment that creates transparency for the work that is required to create a usable Increment that is 'Done'. It is a shared understanding within the Scrum Team of what it means for work to be complete." This reinforces that "Done" is the measure of completeness.