Given Data
Start Date: April 1, 2002.
Duration of Activity 7001 (Normal Schedule): 48 days.
Workweek: 5-day workweek (Monday to Friday).
No holidays are mentioned in the problem.
Step 1: Calculate Total Working Days
Using a 5-day workweek:
Determine the number of full weeks in 48 days:
48÷5=9 weekswith3additionalworkdays.48 \div 5 = 9 \, \text{weeks with 3 additional
workdays.}48÷5=9weekswith3additionalworkdays.
Total work period = 9 weeks + 3 workdays = 45 weekdays.
Step 2: Calculate Calendar End Date
Starting from April 1, 2002 (Monday):
Add 9 full weeks: April 1 + 9 weeks = May 31, 2002 (Friday).
Add the remaining 3 workdays:
Monday, June 3.
Tuesday, June 4.
Wednesday, June 5, 2002.
Step 3: Validate Answer
The finish date for Activity 7001 is June 5, 2002.