Q: 13
There is only enough room for a maximum of 4 cranes to be placed on-site. Assuming that a single
crane can perform 35 lifts per day and that a column pour requires 60 lifts, what is the minimum
number of tower cranes that should be used for the above described column pours?


Options
Discussion
No comments yet. Be the first to comment.