Q: 6
During a Sprint Review, the Product Owner determines that she is going to release the current
Increment to production. The stakeholders ask to stop the Sprint to react more quickly to the user
feedback that is expected after this release. The Product Owner prefers to continue the Sprint to
make progress with the next release. You facilitate a discussion on how to proceed.
What are two acceptable results of this discussion?
(choose the best two answers)