Q: 4
One of the Project Managers in your company has reached out to you to resolve an issue. Many of the Timecards that were approved in the last week against projects are not reflecting back on the Project Actuals. You check that the Actuals Configuration Group > Calculation Mode option is set to "Scheduled". What is the next step you should take?