Q: 9
An architecture firm has a C401 agreement with their consultants for a new design-bid-build residential tower. The architect has approved a schedule provided by the mechanical engineer that includes a two-week quality control review after each delivery milestone. During the design development phase, the owner requests that the architect change the 8,000- square-foot business center amenity for tenants to a private restaurant. The mechanical engineer informs the architect that their schedule must be extended by four weeks to meet the owner's request. What should the architecture firm do first to maintain the start of construction?
Options