Q: 9
An architecture firm has a C401 agreement with their consultants for a new design-bid-build
residential tower. The architect has approved a schedule provided by the mechanical engineer that
includes a two-week quality control review after each delivery milestone.
During the design development phase, the owner requests that the architect change the 8,000-
square-foot business center amenity for tenants to a private restaurant. The mechanical engineer
informs the architect that their schedule must be extended by four weeks to meet the owner's
request.
What should the architecture firm do first to maintain the start of construction?