Q: 12
Near the end of a routine job site visit, the architect begins to assemble notes. The owner's
representative then arrives on site unexpectedly. The architect, owner's representative, and
contractor discuss and resolve several outstanding project issues. The architect begins writing
correspondence to distribute to the project team when the architect returns to the office.
In addition to a Meeting Record, which of the following documents should the architect create?
Options
Discussion