1. American Institute of Architects (AIA) Document A201-2017, General Conditions of the Contract for Construction.
Section 9.8.1: Defines Substantial Completion as "the stage in the progress of the Work when the Work or designated portion thereof is sufficiently complete in accordance with the Contract Documents so that the Owner can occupy or utilize the Work for its intended use."
2. The American Institute of Architects, The Architect's Handbook of Professional Practice, 15th Edition. Wiley, 2013.
Chapter 10.5, "Project Closeout," page 758: "Substantial completion is the point at which the project is sufficiently complete to be occupied or used for its intended purpose... The date of substantial completion is a very important milestone in the project, as it marks the end of the construction period and the beginning of the warranty period."
3. Glower, C. & Glower, S. (2021). The Architect's Legal Handbook (10th ed.). Routledge.
Chapter 10, "The Building Contract," Section 10.5.3, "Completion": This section distinguishes between practical completion (a UK term analogous to substantial completion) and final completion, clarifying that the former is about the building being ready for its intended use, even with minor defects outstanding. (DOI: https://doi.org/10.4324/9781003053957)