Q: 8
Two weeks after starting work the Team Manager noticed that each completed product had
exceeded its estimated effort by around 10%. If this trend continues the Work Package will
exceed its agreed cost tolerance of 5%.
Which 2 actions should the Team Manager take in response to this situation?
Options