1. AXELOS. (2017). Managing Successful Projects with PRINCE2® 6th Edition. TSO (The Stationery Office).
For Correct Answer (B): The 'Starting Up a Project' process objectives include to "ensure that the roles and responsibilities for the work of initiating the project are defined" and its activities include "Design and appoint the project management team". The output is the Project Brief containing the project management team structure. (See Chapter 14
Sections 14.1
14.2
and 14.4.5). This establishes that the initial understanding of roles is an objective of SU
not IP.
For Incorrect Options (A
C
D): The objectives of the 'Initiating a Project' process are explicitly listed and include ensuring a common understanding of "the scope of what is to be done" (A)
"how the quality required will be achieved" (C)
and "how progress will be monitored and controlled" (D). These are documented in the PID
the main output of this process. (See Chapter 15
Section 15.2).