1. AXELOS
"Managing Successful Projects with PRINCE2® 6th Edition" (2017).
For Correct Answer (A): Chapter 18
'Initiating a Project'
describes the purpose of this process is to "establish solid foundations for the project" (Section 18.1). The activities include creating the various strategies and the Project Plan. A risk impacting these activities must be managed within this stage. Appendix A.14
'Initiation Stage Plan'
confirms it contains the "plan for the initiation stage".
For Incorrect Option (B): Chapter 17
'Starting up a Project'
Section 17.1
states the purpose is to ensure the prerequisites for initiating a project are in place. The trigger is the project mandate
and a key output is the approved Project Brief
which is used to request authorization to start the initiation stage (Section 17.4.6).
For Incorrect Option (C): Chapter 19
'Controlling a Stage'
and Chapter 20
'Managing Product Delivery'
describe the work that occurs after initiation. Procurement activities
such as issuing a request for proposals
would be part of a work package managed within these processes
and therefore planned in a delivery Stage Plan
not the Initiation Stage Plan.