Question 7 Q: 7 Which describes a time-driven control? Options A: The dates for the project's end stage assessment included in the project plan B: The expected frequency of progress reports specified in a work package C: The expected dates for planned checks of specialist products included in a stage plan D: The planned exception assessment meeting to authorize a requested exception plan Save Question Show Answer Discussion 0 Clear Discussion Most voted Newest No comments yet. Be the first to comment. Post Be respectful. No spam. Correct Answer: B Explanation A time-driven control is defined as a monitoring system that is based on a fixed time interval, such asweekly or monthly progress reports. The expected frequency of progress reports specified in a workpackage represents a time-driven control, where updates are required at predefined intervalsirrespective of the state of the project at those times.Reference: = PRINCE2® 7 Foundation handbook and online resources