Question 17 Q: 17 Which control is time-driven? Options A: The creation of a highlight report B: The completion of the PID C: The creation of an exception report D: The end of the financial year Save Question Show Answer Discussion 0 Clear Discussion Most voted Newest No comments yet. Be the first to comment. Post Be respectful. No spam. Correct Answer: A Explanation In PRINCE2®, the creation of a highlight report is a time-driven control, typically scheduled at regularintervals, such as weekly or monthly during a stage. This report provides the Project Board and otherstakeholders with a summary of the stage status, and it is triggered by the passage of time, not byspecific events or exceptions within the project.Reference: = PRINCE2® 7 Foundation Training Manual and official PRINCE2® website documentation