In PRINCE2 Agile, a Backlog is the prioritized list of requirements, features, or user stories that define
what needs to be delivered for a product. It is a dynamic and evolving list that is continually refined
and re-prioritized to ensure the most valuable work is done first. The backlog acts as a single source
of truth for what the team needs to deliver and provides transparency to stakeholders regarding
progress and priorities. It aligns with agile principles and practices such as Scrum, where the Product
Backlog contains all desired work for the product.
The Project Canvas is a high-level tool used for defining project scope and objectives, the Release
Map plans releases and iterations, and the Project Log tracks issues, risks, and actions but does not
list prioritized requirements.
Reference: PRINCE2 Agile Foundation Version 2, Section 5.3 "Agile Concepts," and PRINCE2 Agile
Study Guide, Chapter 5, "Products and Backlogs."