DRAG DROP Drag the communication event on the left to the main subject discussed during the event on the right. 
Careful here, the common mix-up is review vs retrospective. Review should be about backlog items completed or not, while retrospective is the continue/stop/start actions. So it's: Daily meeting → development flow, retrospective → continue/stop/start, planning → goal for iteration, review → backlog done or not. Pretty sure that's right but open to alternate views.
Seen similar on practice exams, and it matches the standard agile events: Goal for this iteration → Iteration planning, Development flow → Daily meeting, Backlog items completed or not → Iteration review, Continue/stop/start actions → Iteration retrospective. Pretty sure that's correct but happy to hear if anyone disagrees.