Q: 1
Marty is the project manager of the recently completed NHK Project. The project was deemed
successful by the project customer and they have signed the formal acceptance documentation.
Marty has written the final project report, released the project team, and completed the lessons
learned documentation. What else should Marty do in the closure of the NHK Project?
Options
Discussion
No comments yet. Be the first to comment.
Be respectful. No spam.
Q: 2
Fred is the project manager of the NHA project. This project has a BAC of $2,456,900 and is sixty
percent complete. Fred has crashed the project, which has driven the project costs to date to
$1,525,140, but his project is five percent more complete than what was planned. What is the
schedule variance for this project that Fred needs to report to the management?
Options
Discussion
No comments yet. Be the first to comment.
Be respectful. No spam.
Q: 3
Fredrick works as a Project Manager for BlueWell Inc. A number of projects are running under his
guidance. You, a team leader of a project, inform Fredrick about the performance in exes of your
project. The schedule performance index (SPI) of your project is 1.325. What does this
figure
indicate?
Options
Discussion
No comments yet. Be the first to comment.
Be respectful. No spam.
Q: 4
You are the project manager for your organization. You are working with your project team to define
the project network diagram. Several of the activities in the project schedule appear to have external
constraints. Who among the following determines which dependencies are external to the project?
Options
Discussion
No comments yet. Be the first to comment.
Be respectful. No spam.
Q: 5
Which of the following is an output of the Identify Stakeholders process?
Options
Discussion
No comments yet. Be the first to comment.
Be respectful. No spam.
Q: 6
You are working as a project manager for BlueWell Inc. Which of the following tools and techniques
of the Define Activity process will help you in identifying the typical schedule milestones?
Options
Discussion
No comments yet. Be the first to comment.
Be respectful. No spam.
Q: 7
Mary is the project manager for her company. She's working with the project team to compress the
project schedule as the project must be completed by December 30. For some of the project
activities, she and the project team have agreed to crash the project work. What must be true of
these project activities for crashing to be acceptable?
Options
Discussion
No comments yet. Be the first to comment.
Be respectful. No spam.
Q: 8
In the project time management knowledge area, there are six processes. According to the PMBOK,
which project time knowledge area will have the majority of the effort?
Options
Discussion
No comments yet. Be the first to comment.
Be respectful. No spam.
Q: 9
Kelly is the project manager of her organization. She is reviewing the project network diagram to
confirm that the resource she has identified is available to complete the project assignments without
conflicting with other activities in the project node. The availability of resources will help Kelly
determine the final finish date for the project. What scheduling technique is Kelly using?
Options
Discussion
No comments yet. Be the first to comment.
Be respectful. No spam.
Q: 10
You are the project manager for your organization. You are working on creating the activity list so
that you can create the project schedule. This current project is similar to a project you have
competed for your company. You and the project team decide to use the previous project as a
template for your current project. A template can help you and the project team do all of the
following except for which one?
Options
Discussion
No comments yet. Be the first to comment.
Be respectful. No spam.
Question 1 of 20 · Page 1 / 2