The Identify Stakeholders process identifies all people or organizations that are impacted by the
project. It also documents relevant information regarding their interests, involvement, and impact
on project success. Stakeholder register and stakeholder management strategy are outputs of this
process. Answer option C is incorrect. Project charter is one of the inputs of the Identify
Stakeholders process. Answer option A is incorrect. Scope baseline is one of the outputs of the
Create Work Breakdown Structure (WBS) process. Answer option B is incorrect. Project scope
statement is one of the outputs of the Define Scope process.