Q: 3
Fredrick works as a Project Manager for BlueWell Inc. A number of projects are running under his
guidance. You, a team leader of a project, inform Fredrick about the performance in exes of your
project. The schedule performance index (SPI) of your project is 1.325. What does this
figure
indicate?