Q: 12
Your project has a BAC of $750,000 and is 75 percent complete. According to your plan, however,
your project should actually be 80 percent complete. You have spent $575,000 of your project
budget to reach this point and you are worried about the project not being able to complete based
on your current project budget. What is the to-complete performance index for this project?