Q: 11
A risk management professional is in the process of categorizing risks when a subject matter expert
(SME) suggests categorizing the risks by their impact to the project objectives. Why should the risk
management professional use this approach?
Options
Discussion
No comments yet. Be the first to comment.
Be respectful. No spam.
Q: 12
A project's design has been completed and approved on time. The construction subcontractor should
be mobilizing to start construction but does not have the necessary materials in place, causing a
delaying in the project. The risk register only contains risks for the design phase of the project.
What should the project manager have done differently?
Options
Discussion
No comments yet. Be the first to comment.
Be respectful. No spam.
Q: 13
A project team has completed the risk identification steps in a project and compiled a list of 25 risks.
The team wants to create response plans for all the risks to avoid any future issues, but the resources
and constraints limit the options.
What should the risk manager do?
Options
Discussion
No comments yet. Be the first to comment.
Be respectful. No spam.
Q: 14
An organization is embarking on a multi-million-dollar project with numerous identified risks. What
should the project risk team do to navigate the risks on this project?
Options
Discussion
No comments yet. Be the first to comment.
Be respectful. No spam.
Q: 15
After presenting a list of risks to the major project stakeholders and project sponsor, the board
requested the risks be sorted differently from the results presented by the project team. This is a
major issue and will cause a 2-week delay in the project.
How could the risk manager have avoided the board's response?
Options
Discussion
No comments yet. Be the first to comment.
Be respectful. No spam.
Q: 16
A risk manager on an infrastructure project gathers and analyzes performance dat
a. The risk manager wants to identify which variables will impact the schedule and determine how
these factors interact.
Which data analysis tool should the risk manager use to forecast future performance?
Options
Discussion
No comments yet. Be the first to comment.
Be respectful. No spam.
Q: 17
A budget change request was initiated by a functional manager in an organization due to a shortage
in the functional manager's department budget. The functional manager asks the CEO to approve
utilization of a contingency budget reserved for one of the projects in its closing phase.
What should the risk manager of the related project have done to prevent this situation from
happening?
Options
Discussion
No comments yet. Be the first to comment.
Be respectful. No spam.
Q: 18
A new company initiates a project to incorporate a cybersecurity team. Which three documents
should the risk manager analyze first? (Choose 3)
Options
Discussion
No comments yet. Be the first to comment.
Be respectful. No spam.
Q: 19
A project manager was informed that the testing of the latest component in the project's software
update release was not successful. As a result, 1he delivery timelines for the software release wifi be
delayed, The project manager did not previously capture this as a risk to the project.
What should the project manager do next to avoid similar risks?
Options
Discussion
No comments yet. Be the first to comment.
Be respectful. No spam.
Question 11 of 20 · Page 2 / 2