Q: 19
A project manager was informed that the testing of the latest component in the project's software
update release was not successful. As a result, 1he delivery timelines for the software release wifi be
delayed, The project manager did not previously capture this as a risk to the project.
What should the project manager do next to avoid similar risks?
Options