Q: 17
A budget change request was initiated by a functional manager in an organization due to a shortage
in the functional manager's department budget. The functional manager asks the CEO to approve
utilization of a contingency budget reserved for one of the projects in its closing phase.
What should the risk manager of the related project have done to prevent this situation from
happening?